Under construction
4
Planned ports

Washington's NEVI story is a story about a mostly-built market. The state's commercial charging network already covers I-5, I-90 west of the Cascades, and the major metros — so NEVI money here is surgical, aimed at the specific rural gaps the market skipped. The flagship is Cle Elum on I-90, a 4-port 350 kW Electric Era site that opened in January 2026 and is the first live NEVI station in our seven-state coverage area. The remaining pipeline targets the I-90 corridor east of the Columbia River, where the 90-mile Moses Lake–Spokane gap has been the state's most persistent charging problem. WSDOT administers the program and publishes awards on its NEVI program page. For what these sites mean on the road today, see our I-90 corridor guide — until Ritzville comes online, the eastern gap still requires planning.

New to the program? Start with NEVI Explained — what the $5 billion program requires (97% uptime, four 150 kW ports minimum), why it paused and restarted in 2025, and how to tell if a station is NEVI-funded.

Washington Sites

Location Corridor Operator Ports Power Status Expected Live Source
Cle Elum, I-90 milepost 84 I-90 Electric Era 4 350 kW live 2026-01-01 Source →

Data sources and methodology

Site list sourced from state DOT NEVI program pages and FHWA grant records, cross-checked against the NREL Alternative Fuels Station Locator. Status verified monthly. Expected live dates are official estimates and regularly slip 3–12 months. For scoring methodology across the site, see how we measure. Related: Washington EV charging hub · Q3 2026 regional status report.